Milestones

2003
Contract sign off with Dupont/Invista on 8 December 2003
Contract sign off with bankers on 8 December 2003
Start of the project on 15 December 2003
2004
Ground breaking ceremony held and piling work begins on 2 June 2004
First structural erection work commences on 10 December 2004
2005
Delivery of first equipment at site 26 February 2005
Pipe testing work started on 15 July 2005
Erection of equipment completed on 20 November 2005
2006
Start of PTA production on 15 March 2006
2007
Received ISO 9001: 2000 certification on 4 May 2007

 

 