| 2003 |
 |
Contract sign off
with Dupont/Invista on 8 December 2003 |
 |
Contract sign off
with bankers on 8 December 2003 |
 |
Start of the project
on 15 December 2003 |
 |
| 2004 |
 |
Ground breaking ceremony
held and piling work begins on 2 June 2004 |
 |
First structural
erection work commences on 10 December 2004 |
 |
| 2005 |
 |
Delivery of first
equipment at site 26 February 2005 |
 |
Pipe testing work
started on 15 July 2005 |
 |
Erection of equipment
completed on 20 November 2005 |
 |
| 2006 |
 |
Start
of PTA production on 15 March 2006 |
 |
| 2007 |
 |
Received
ISO 9001: 2000 certification on 4 May 2007 |