October 2004
Indorama Newsroom
PT Indorama Synthetics Tbk is planning
to meet its electricity requirement by setting up a
Captive Power plant at its principal manufacturing facility
located at Purwakarta, Indonesia.
The management has taken initiative
amid possibilities of further rise in power tariffs
due to removal of all subsidies on fuel and decided
to invest in its own power generation plant.
The Plan is to construct 2 x 30 MW
coal based co-generation power plant spread over an
area of 16 hectares at its existing manufacturing facility
located at Purwakarta.
The EPC contract has been awarded
to China Huadian Engineering Co, China with long term
financing provided by International Finance Corporation,
the private sector arm of the World Bank.

|